FCDL Comment:
MR1:The Contract Expiration Date was changed from 06/30/2019 to 06/30/2029 to agree with the documentation provided during the review of the FCC Form 471.||MR2:The Total Strands for FRN Line Item 001 was modified from 2 to 192 to agree with the applicant documentation.||MR3:The Number of E-Rate Eligible Strands for FRN Line Item 001 was modified from 2 to 96 to agree with the applicant documentation.||MR4:The Total Project Plant Route Feet for FRN Line Item 001 was modified from 301382 to 343622 to agree with the applicant documentation.||MR5:The Average Cost Per Foot of Outside Plant for FRN Line Item 001 was modified from $4.90 to $4.30 to agree with the applicant documentation.||MR6:The State/Tribal E-Rate Match Amount for FRN Line Item 001 was modified from $1,478,646.05 to $73,932.00 to agree with the applicant documentation.