Billed Entity:
140062
FRN:
1799082322
Funding Year:
2017
470#:
170055759
471#:
171030597
Category of Service:
INTERNET ACCESS
Status:
Funded
FCDL Date:
2017-11-22
Wave:
26
FCDL Comment:
MR1:The Total Project Plant Route Feet and Average Cost Per Foot of Outside Plant was modified from 43,243 route feet and $11.40/foot to 59,748 route feet and $8.11/foot to agree with the applicant documentation.||MR2:The FRN was modified from $484,329.00 to $473,941.50 to agree with the applicant documentation.||MR3:Per FCC Order 14-189, to prevent warehousing of excess fiber capacity, applicants may only receive funding for special construction charges for Leased Lit Fiber or Leased Dark Fiber if it is lit within the same funding year. If excess strands are being installed that will not be lit during the current FY and will be used by an ineligible entity or for an ineligible purpose; the applicant must provide a cost allocation for any variable costs of installing a higher strand cable as opposed to installing the strands needed just for the applicant’s exclusive use. The amount of the funding request was changed from $473,941.50 to $455,782.50 to remove $18,159.00 associated with ineligible excess fiber capacity.||MR4:Documentation provided indicates that your Funding Request is for unlit Dark Fiber. Do not submit invoices until the fiber is lit. Please provide documentation that it is lit when submitting your invoice.
Service Start Date (471):
2018-03-20
Service Start Date (486):
2018-03-20
Committed Amount:
$431,580.45
Last Date of Service:
2019-06-30
Disbursed Amount:
$431,580.45
Payment Mode:
SPI
Remaining:
$0.00
Last Date to Invoice:
2019-10-28

Original
Committed
Monthly Cost:
$0.00
$0.00
Ineligible Monthly Cost:
$0.00
$0.00
Months of Service:
12
4
Annual Recurring Charges:
$0.00
$0.00
One Time Cost:
$484,329.00
$473,941.50
One Time Ineligible Cost:
$0.00
$455,782.50
Total Cost:
$484,329.00
$455,782.50
Discount Percent:
95
95
Requested Amount:
$460,112.55
$431,580.45