Billed Entity:
129531
FRN:
1899053369
Funding Year:
2018
470#:
180021272
471#:
181028277
Category of Service:
INTERNAL CONNECTIONS
Status:
Funded
FCDL Date:
2019-10-07
Wave:
64
FCDL Comment:
MR1:The funding request amount was reduced from $885,195.50 to $615,237.46 to remove the amount that exceeded the Category Two budget set for the following entities: 48259 - CUYAHOGA FALLS HIGH SCHOOL, 48257 - ROBERTS MIDDLE SCHOOL, 48270 - BOLICH MIDDLE SCHOOL, 48276 - SILVER LAKE ELEMENTARY SCHOOL, and 16029687 - SCHNEE LEARNING CENTER.
Service Start Date (471):
2018-07-01
Service Start Date (486):
2018-07-01
Committed Amount:
$369,142.48
Last Date of Service:
2020-09-30
Disbursed Amount:
$369,142.48
Payment Mode:
SPI
Remaining:
$0.00
Last Date to Invoice:
2022-01-28

Original
Committed
Monthly Cost:
$0.00
$0.00
Ineligible Monthly Cost:
$0.00
$0.00
Months of Service:
12
12
Annual Recurring Charges:
$0.00
$0.00
One Time Cost:
$885,195.50
$615,237.46
One Time Ineligible Cost:
$0.00
$615,237.46
Total Cost:
$885,195.50
$615,237.46
Discount Percent:
60
60
Requested Amount:
$531,117.30
$369,142.48